ENTERPRISE PRODUCTS LABORATORY & OFFICE
Mont Belvieu, TX
Client:
Enterprise Products
Contractor:
Brewer Construction Services
Size:
14,000 gsf / 10 acre site
Completion:
Q3 2020
Construction Cost:
$11,000,000
Delivery Method:
Design-Build
The new QA/QC Operations Laboratory is designed to support refinery production while ensuring compliance with federal, state, and industry standards through rigorous testing of all outbound chemical shipments—whether by rail, truck, or pipeline. Featuring key infrastructure such as an on-site oxidizer, fire detention pond, radio tower, and a spacious yard, the facility highlights its shared laboratory spaces through thoughtfully designed visual connections between visitor areas and active work zones—showcasing both transparency and technical excellence.
Key Features:
-
Comprehensive QA/QC Operations Laboratory
-
Safety-focused infrastructure (oxidizer, fire detention pond, radio tower)
-
Transparent, collaborative laboratory design